Construction Timeline & Schedule Planner

Build a construction schedule with tasks, durations and dependencies. The planner computes start and finish dates, flags the critical path, draws a Gantt chart, and shows total project duration and end date from your start date.

Project
Add Task
Project Summary
Gantt & Tasks

About Construction Timeline & Schedule Planner

A building project is a chain of dependent steps: demo before rough-in, rough-in before inspection, inspection before finish. The Construction Timeline & Schedule Planner turns that chain into a real schedule. Enter each task with a duration and its predecessor, set a start date, and the tool computes every start and finish date, flags the critical path, and draws a Gantt chart.

You get the total project duration, the end date, and a clear view of which tasks have slack and which do not. Adjust durations or dependencies and the whole plan recomputes live so you can pressure-test the schedule before a shovel hits the ground.

Features

  • Dependency engine: Forward-pass scheduling from predecessors.
  • Critical path: Zero-slack tasks flagged automatically.
  • Gantt chart: Visual bars positioned by start and duration.
  • Slack & dates: Start, finish and slack per task.
  • Project totals: Total duration and end date from start date.
  • Parallel work: Independent tasks overlap correctly.
  • Export: CSV, JSON or plain text of the full schedule.

How to Use

  1. Start date. Set the project start.
  2. Add tasks. Name, duration in days, and a predecessor (or none).
  3. Sequence. Chain tasks so each starts after the right finish.
  4. Review. Read the Gantt and the critical-path flags.
  5. Adjust. Change durations or links and watch totals update.
  6. Export. Save the schedule for the team or client.

Examples

Example 1 — Linear build. Demo → framing → rough-in → inspection → finish: each waits for the prior, so total is the sum.

Example 2 — Overlap. Electrical and plumbing both follow rough-in with no link to each other: they run in parallel on the Gantt.

Example 3 — Critical slip. Stretch the foundation task and every downstream task shifts; the critical flag shows the impact.

Example 4 — Buffer. Add float by giving a non-critical task slack; the end date does not move.

Example 5 — Two predecessors. Inspection waits for both electric and plumbing, starting at the later finish.

Benefits

  • See the end date: Know when the project truly finishes.
  • Find the risk: Critical tasks are where delays hurt most.
  • Communicate: A Gantt explains sequencing to clients fast.
  • Test scenarios: Replan in seconds by editing durations.
  • Parallelize: Spot where work can overlap to save time.
  • Private: No account, no upload, nothing stored.

Frequently Asked Questions

How are start dates calculated?
Each task starts when its predecessor finishes (or on the project start date if it has none). The planner runs a forward pass so every date is consistent with the dependencies you enter.
What is the critical path?
Tasks with zero slack — any delay pushes the whole project — are marked critical. The planner approximates this by comparing each task’s finish to the project’s latest finish.
Can tasks run in parallel?
Yes. Tasks with no dependency on each other start as soon as possible and overlap on the Gantt chart. Only a predecessor forces a wait.
What if a task has two predecessors?
It starts after the later of the two finishes, matching how real sequencing works when multiple things must complete first.
How is total duration shown?
Total duration is the calendar span from project start to the latest task finish, not the sum of all task days, because parallel work overlaps.
Does it add weekends?
The dates are calendar days for simplicity. For crew-only working days, add buffer to task durations or pad the schedule.
Can I export the schedule?
Yes — CSV, JSON or plain text with each task’s start, finish, slack and critical flag, plus the Gantt as a list.
Is my data stored?
No. All scheduling runs in your browser; nothing is uploaded, saved or logged.